Which event takes place at the start of a sprint?

Prepare for the Mendix Intermediate Certification Exam using engaging quizzes! Access multiple-choice questions, hints, and detailed explanations. Ace your test!

At the beginning of a sprint, sprint planning is the key event that occurs. During sprint planning, the team collaborates to define what work will be accomplished during the upcoming sprint. This involves selecting items from the product backlog that align with the sprint goal and discussing how the team will deliver those items. The activities include estimating tasks, defining the sprint goal, and ensuring that everyone understands the work needed to achieve the objectives.

This event is crucial because it sets the stage for the entire sprint, allowing team members to align on priorities, clarify expectations, and establish a shared understanding of the tasks at hand. By engaging in sprint planning, the team can maximize their efficiency and effectiveness as they head into the sprint.

The other events mentioned serve different purposes within the sprint cycle: the sprint review assesses the work completed at the end of the sprint, the daily scrum is a stand-up meeting for quick updates and status checks, and the sprint retrospective focuses on reflecting on the sprint to identify improvements for future iterations. Each of these events is important in its own right, but sprint planning is specifically designed to kick off the sprint effectively.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy